# Procurement Flow Design v1
## 1. Executive Summary
**Задача:** 006-procurement-flow-design-v1
**Дата:** 07 October 2026
**Рабочая директория:** `/mnt/nas/hermes-test/Specs`
**Тип:** Design Task (не implementation)
**Цель:** Спроектировать procurement контур Purchase/PurchaseItem/Invoice/Resource/ResourceAllocation.
**Статус:** ✅ Design report создан
---
## 2. Current Model Analysis
### 2.1 Фактические модели
```
Purchase
├─ project_id (FK → Project)
├─ vendor_id (FK → Vendor)
├─ purchase_number
├─ purchase_date
└─ specifications (M:N → Specification через PurchaseSpecification)
PurchaseItem
├─ purchase_id (FK → Purchase)
├─ module_id (FK → Module)
├─ quantity (Integer)
├─ unit_price (Numeric)
└─ description (Text)
PurchaseSpecification
├─ purchase_id (PK, FK → Purchase)
└─ specification_id (PK, FK → Specification)
Invoice
├─ purchase_id (FK → Purchase)
├─ vendor_id (FK → Vendor)
├─ invoice_number
├─ invoice_date
├─ amount (Numeric)
└─ description (Text)
Specification
├─ project_id (FK → Project)
├─ contract_id (FK → Contract)
├─ specification_number
├─ specification_date
└─ specifications (M:N → Purchase через PurchaseSpecification)
SpecificationItem
├─ specification_id (FK → Specification)
├─ module_id (FK → Module)
├─ quantity (Integer)
└─ description (Text)
Resource
├─ project_id (FK → Project)
├─ module_id (FK → Module)
├─ quantity (Integer)
├─ invoice_number (String)
├─ invoice_date (DateTime)
├─ specification_number (String)
├─ specification_id (FK → Specification, nullable)
├─ invoice_id (FK → Invoice, nullable)
└─ description (Text)
ResourceAllocation
├─ resource_id (FK → Resource)
├─ system_id (FK → System)
├─ guardian_id (FK → Guardian, nullable)
├─ quantity (Integer)
└─ allocation_date (DateTime)
```
### 2.2 Фактические relationships
| Relationship | Direction | Cardinality |
|--------------|-----------|-------------|
| Purchase.specifications | Purchase → Specification | 1:N |
| PurchaseItem.purchase | PurchaseItem → Purchase | N:1 |
| Invoice.purchase | Invoice → Purchase | N:1 |
| Specification.purchases | Specification → Purchase | 1:N |
| SpecificationItem.specification | SpecificationItem → Specification | N:1 |
| Resource.invoice | Resource → Invoice | N:1 |
| Resource.specification | Resource → Specification | N:1 (nullable) |
| Resource.module | Resource → Module | N:1 |
| ResourceAllocation.resource | ResourceAllocation → Resource | N:1 |
### 2.3 Constraints
**PurchaseSpecification:**
- PK: (purchase_id, specification_id)
- FK: purchase_id → Purchase.id (CASCADE)
- FK: specification_id → Specification.id (CASCADE)
**PurchaseItem:**
- FK: purchase_id → Purchase.id (CASCADE)
- FK: module_id → Module.id (RESTRICT)
**Resource:**
- FK: project_id → Project.id (CASCADE)
- FK: module_id → Module.id (RESTRICT)
- FK: invoice_id → Invoice.id (SET NULL)
- FK: specification_id → Specification.id (SET NULL)
- Check: quantity > 0
---
## 3. Real Procurement Scenarios
### 3.1 Сценарий A — одна закупка, одна спецификация
```
Purchase #1
└─ Specification #18
└─ Invoice #145
└─ Resource: Camera ×2000
```
**Реализация:** ✅ Поддерживается
- Purchase → Specification через PurchaseSpecification
- Invoice → Purchase
- Resource → Invoice + Resource → Specification
### 3.2 Сценарий B — одна закупка, несколько спецификаций
```
Purchase #1
├─ Specification #18
└─ Specification #27
```
**Реализация:** ✅ Поддерживается
- M:N связь Purchase ↔ Specification через PurchaseSpecification
- Одна запись Purchase может иметь много записей PurchaseSpecification
### 3.3 Сценарий C — одна закупка, несколько Invoice
```
Purchase #1
├─ Invoice #145
└─ Invoice #146
```
**Реализация:** ✅ Поддерживается
- Invoice → Purchase (N:1)
- Одна Purchase может иметь много Invoice
### 3.4 Сценарий D — один Invoice, несколько Resource
```
Invoice #145
├─ Camera ×2000
├─ Agent ×100
└─ Tracker ×50
```
**Реализация:** ✅ Поддерживается
- Resource → Invoice (N:1)
- Одна Invoice может быть источником многих Resource
### 3.5 Сценарий E — один Module из нескольких закупок
```
Camera:
Resource #1 → Invoice #101 → Spec #12 → ×1000
Resource #2 → Invoice #145 → Spec #18 → ×2000
Resource #3 → Invoice #201 → Spec #27 → ×2000
```
**Реализация:** ✅ Поддерживается
- Каждый Resource имеет независимый ID
- Provenance сохраняется для каждого Resource
### 3.6 Сценарий F — один Resource распределяется в несколько систем
```
Resource Camera ×2000
├─ System A / Guardian 1 → ×300
├─ System B / Guardian 2 → ×700
└─ System B / Common → ×400
remaining = 600
```
**Реализация:** ✅ Поддерживается (уже реализовано в 004)
- ResourceAllocation → Resource (N:1)
- Остаток рассчитывается как `Resource.quantity - SUM(ResourceAllocation.quantity)`
---
## 4. PurchaseItem vs Resource
### 4.1 PurchaseItem семантика
**Purpose:** Позиция в закупке (ordered quantity)
```
PurchaseItem
├─ Module = Camera
├─ Ordered quantity = 2000
├─ Unit price = $100.00
└─ Description = "License modules"
```
**Характеристики:**
- Представляет **обязательство** закупить Module
- Количество — **заказанное** (ordered)
- Цена — **ценовое обязательство** (unit_price)
- Не изменяется после создания (историческая запись)
### 4.2 Resource семантика
**Purpose:** Фактически полученная партия (received quantity)
```
Resource
├─ Module = Camera
├─ Received quantity = 2000
├─ Invoice = #145
├─ Specification = #18
└─ Invoice date = 2026-10-07
```
**Характеристики:**
- Представляет **фактическое поступление** Module
- Количество — **полученное** (received)
- Связан с Invoice и Specification
- Может быть распределён в Systems
### 4.3 Ключевое различие
| Аспект | PurchaseItem | Resource |
|--------|--------------|----------|
| **Nature** | Ordered / Agreed | Received / Actual |
| **Quantity** | Заказано | Поступило |
| **Price** | unit_price | Не хранит цену |
| **Immutability** | Историческая запись | Меняется (allocation) |
| **Provenance** | Purchase | Invoice + Specification |
### 4.4 Decision: Resource → PurchaseItem связь
**Вариант A (без прямой связи):**
```
Resource
├─ Invoice → Purchase → PurchaseItem
└─ Specification
```
**Вариант B (с прямой связью):**
```
Resource
├─ Invoice → Purchase
├─ Specification
└─ PurchaseItem (FK)
```
**Decision:** **Вариант A** (без прямой связи)
**Reason:**
1. Provenance цепочка через Invoice достаточно однозначна
2. Resource → Specification (опционально) уже связывает с SpecificationItem
3. Добавление FK увеличит сложность без существенной выгоды
4. Можно найти PurchaseItem через:
- `Invoice.purchase_id → Purchase.purchase_id`
- `Purchase.purchase_id → PurchaseItem.purchase_id`
- Фильтрация по `module_id`
**Current model impact:**
- Никаких изменений в модели
- Никаких миграций не требуется
---
## 5. Invoice Semantics
### 5.1 Текущая модель
```
Invoice
├─ purchase_id (FK → Purchase)
├─ vendor_id (FK → Vendor)
├─ invoice_number
├─ invoice_date
├─ amount (Numeric)
└─ description (Text)
```
### 5.2 Проверяемые вопросы
| Вопрос | Ответ | Обоснование |
|--------|-------|-------------|
| Invoice относится к Purchase? | ✅ Да | `purchase_id` FK |
| Один Purchase может иметь несколько Invoice? | ✅ Да | N:1 (N Invoice → 1 Purchase) |
| Один Invoice может содержать несколько PurchaseItem? | ❌ Нет | Invoice не имеет прямой связи с PurchaseItem |
| Один Invoice может порождать несколько Resource? | ✅ Да | N:1 (N Resource → 1 Invoice) |
| Как определяется Project Invoice? | Через Purchase | `Invoice → Purchase → Project` |
### 5.3 Invoice ↔ Project связь
**Факт:** Invoice не имеет direct `project_id`
**Provenance:**
```
Resource → Invoice → Purchase → Project
```
**Decision:** Текущей косвенной связи **достаточно**
**Reason:**
1. Purchase имеет `project_id` — это определяет Project закупки
2. Invoice не может принадлежать к другому Project, чем Purchase
3. Прямой `project_id` у Invoice избыточен (нарушает нормальную форму)
4. Все проверки через Purchase работают корректно
**Gap:** Проверка Invoice ↔ Project требует JOIN через Purchase
```sql
SELECT * FROM Invoice
JOIN Purchase ON Invoice.purchase_id = Purchase.id
WHERE Purchase.project_id = ?
```
**Рекомендация:** Добавить `project_id` к Invoice для оптимизации
- **NOT в рамках 006** — отдельная архитектурная задача
---
## 6. Specification Semantics
### 6.1 Текущая модель
```
Specification
├─ project_id (FK → Project)
├─ contract_id (FK → Contract)
├─ specification_number
├─ specification_date
└─ specifications (M:N → Purchase через PurchaseSpecification)
SpecificationItem
├─ specification_id (FK → Specification)
├─ module_id (FK → Module)
├─ quantity
└─ description
PurchaseSpecification
├─ purchase_id (PK, FK → Purchase)
└─ specification_id (PK, FK → Specification)
```
### 6.2 Проверяемые вопросы
| Вопрос | Ответ | Обоснование |
|--------|-------|-------------|
| Specification принадлежит Project? | ✅ Да | `project_id` FK |
| Purchase может быть связан с несколькими Specification? | ✅ Да | M:N через PurchaseSpecification |
| Resource может ссылаться на Specification напрямую? | ✅ Да | `specification_id` nullable FK |
| Если Purchase связан с несколькими Specification, как однозначно определить Specification конкретного Resource/Invoice? | ⚠️ **Ambiguous** | Resource → Specification (опционально) |
| Может ли один Invoice содержать ресурсы для нескольких Specification? | ⚠️ **Неясно** | Resource → Invoice (N:1), Resource → Specification (N:1 nullable) |
### 6.3 Critical Ambiguity
**Проблема:** Если Purchase имеет несколько Specification:
```
Purchase #10
├─ Spec #18
└─ Spec #27
Invoice #145
├─ Camera ×1000 → Spec #18 (через Resource.specification_id)
└─ Camera ×500 → Spec #27 (через Resource.specification_id)
```
**Вопрос:** Как однозначно определить, к какой Specification относится Resource?
**Текущий механизм:** Resource.specification_id
**Проблема:**
- `specification_id` в Resource **опционально** (nullable)
- Нет механизма принудительного указания Specification
- Если `specification_id` NULL, происхождение неясно
**Decision:** Текущая модель **допускает неоднозначность**
**Reason:**
1. Specification опциональна для Resource
2. Нет проверки на уровне модели
3. Проверка должна быть в Service layer
**Gap:** Нет явного механизма для случаев, когда Purchase имеет несколько Specification
**Рекомендация:** Сделать `specification_id` **обязательным** или добавить `InvoiceSpecification` ассоциацию
---
## 7. Provenance Chain
### 7.1 Окончательная цепочка
```
Specification (customer need)
↓
PurchaseSpecification (link)
↓
Purchase (procurement action)
↓
PurchaseItem (ordered module)
↓
Invoice (payment document)
↓
Resource (received module)
↓
ResourceAllocation (distribution)
↓
System / Guardian / Common (usage)
```
### 7.2 Каждый шаг
| Шаг | Entity | Purpose | FK Links |
|-----|--------|---------|----------|
| 1 | Specification | Потребность заказчика | project_id, contract_id |
| 2 | PurchaseSpecification | Связь Purchase ↔ Specification | purchase_id, specification_id |
| 3 | Purchase | Закупка у поставщика | project_id, vendor_id |
| 4 | PurchaseItem | Позиция в закупке | purchase_id, module_id |
| 5 | Invoice | Счёт поставщика | purchase_id, vendor_id |
| 6 | Resource | Фактически полученная партия | project_id, module_id, invoice_id, specification_id |
| 7 | ResourceAllocation | Распределение в системы | resource_id, system_id, guardian_id |
| 8 | System/Guardian/Common | Использование | - |
### 7.3 Инварианты
1. **Resource всегда относится к Project** ✅ enforced через `project_id` FK
2. **Resource всегда относится к Module** ✅ enforced через `module_id` FK
3. **Resource всегда относится к Invoice** ✅ enforced через `invoice_id` FK
4. **Specification у Resource либо отсутствует, либо относится к тому же Project** ⚠️ **проверка в Service**
5. **Resource quantity > 0** ✅ enforced через CheckConstraint
6. **Resource не должен смешивать разные Invoice/Specification** ✅ enforced через FK
7. **Один Invoice может породить много Resource** ✅ enforced через N:1
8. **Один Module может иметь много Resource** ✅ enforced через N:1
9. **Один Resource может иметь много ResourceAllocation** ✅ enforced через N:1
10. **Сумма ResourceAllocation не может превышать Resource.quantity** ✅ enforced в Service
---
## 8. Decision Log
### 8.1 Decision: Resource → PurchaseItem
| Attribute | Value |
|-----------|-------|
| **Decision** | Без прямой FK связи (Вариант A) |
| **Reason** | Провенанс через Invoice → Purchase → PurchaseItem однозначен |
| **Current model impact** | Никаких изменений |
### 8.2 Decision: InvoiceSemantics
| Attribute | Value |
|-----------|-------|
| **Decision** | Текущей косвенной связи достаточно |
| **Reason** | Invoice → Purchase → Project работает корректно |
| **Current model impact** | Никаких изменений |
### 8.3 Decision: InvoiceItem
| Attribute | Value |
|-----------|-------|
| **Decision** | **Не создавать** InvoiceItem |
| **Reason** | Текущая модель PurchaseItem/Invoice/Resource достаточно для всех сценариев |
| **Current model impact** | Никаких изменений |
### 8.4 Decision: Specification Ambiguity
| Attribute | Value |
|-----------|-------|
| **Decision** | Оставить nullable specification_id |
| **Reason** | Некоторые Resource могут быть общими для нескольких Specification |
| **Current model impact** | Никаких изменений, но Service layer должен проверять Project match |
---
## 9. Business Invariants
### 9.1 Enforced by Database
| # | Invariant | Enforcement |
|---|-----------|-------------|
| 1 | Resource.project_id > 0 | NOT NULL FK |
| 2 | Resource.quantity > 0 | CheckConstraint |
| 3 | ResourceAllocation.quantity > 0 | CheckConstraint |
| 4 | PurchaseSpecification уникальность | PK (purchase_id, specification_id) |
| 5 | PurchaseItem уникальность | PK (purchase_item_id) |
### 9.2 Enforced by Service Layer
| # | Invariant | Enforcement |
|---|-----------|-------------|
| 1 | Specification принадлежит тому же Project | `specification.project_id == project_id` |
| 2 | Invoice принадлежит тому же Project | `Invoice.purchase.project_id == project_id` |
| 3 | Resource.quantity не превышает остаток | `SUM(allocations) + quantity <= resource.quantity` |
| 4 | Module существует | Query Module before use |
---
## 10. Gaps & Follow-up
### 10.1 Gap 1: Invoice → Project indirect link
**Problem:** Invoice не имеет direct `project_id`
**Impact:** Проверка требует JOIN через Purchase
**Recommendation:** Добавить `project_id` к Invoice
- **NOT в рамках 006** — отдельная архитектурная задача
- **Risk:** Нарушение нормализации (дублирование Project reference)
### 10.2 Gap 2: Specification ambiguity
**Problem:** Если Purchase имеет несколько Specification, ambiguous определить Specification конкретного Resource
**Impact:** Resource без `specification_id` имеет неясное происхождение
**Recommendation:**
- Вариант A: Сделать `specification_id` обязательным для Resource
- Вариант B: Добавить `InvoiceSpecification` ассоциация
### 10.3 Gap 3: Purchase vs Resource quantity
**Problem:** Нет явного distinction между ordered и received quantity
**Impact:**
- `PurchaseItem.quantity` — ordered
- `Resource.quantity` — received
- Нет проверки `received <= ordered`
**Recommendation:** Добавить constraint в Service layer
- Проверять `Resource.quantity <= SUM(PurchaseItem.quantity)`
### 10.4 Gap 4: Partial delivery
**Problem:** Нет поддержки частичных поставок
**Impact:**
- Заказано 2000, получено 1800
- Нет механизма "оставшиеся 200"
**Recommendation:**
- Добавить `received_quantity` к PurchaseItem
- Или использовать Resource для каждой частичной поставки
---
## 11. Recommended Next Implementation Task
### 11.1 Task: 007-ProvenanceValidationService
**Title:** Service layer validation для procurement provenance
**Scope:**
1. Service `ProvenanceValidationService`
2. Проверка Specification ↔ Project match
3. Проверка Invoice ↔ Project match (через Purchase)
4. Проверка ordered vs received quantity
5. Проверка частичных поставок (optional)
**Files to create:**
- `app/services/provenance_validation_service.py`
- `tests/test_provenance_validation.py`
**Files to modify:**
- `ResourceReceiptService.receive_resource()` — добавить validation
- `ResourceAllocationService.allocate_resource()` — добавить validation
**Estimated effort:** 1-2 дня
### 11.2 Alternative Task: 007-ProvenanceQueryService
**Title:** Service для query procurement provenance chain
**Scope:**
1. Service `ProvenanceQueryService`
2. Метод `get_provenance_chain(resource_id)`
3. Метод `get_ordered_received_allocated_quantities(resource_id)`
4. Метод `get_purchases_by_specification(specification_id)`
**Files to create:**
- `app/services/provenance_query_service.py`
- `tests/test_provenance_query.py`
**Files to modify:**
- Никаких изменений в existing services
**Estimated effort:** 1 день
---
## 12. Summary
### 12.1 Фактические модели
- **Purchase/PurchaseItem/PurchaseSpecification** — procurement (ordered)
- **Invoice** — payment document
- **Resource** — received module
- **ResourceAllocation** — distribution
### 12.2 Фактические связи
- **Purchase ↔ Specification** — M:N через PurchaseSpecification
- **Invoice → Purchase** — N:1
- **Resource → Invoice** — N:1
- **Resource → Specification** — N:1 (nullable)
- **ResourceAllocation → Resource** — N:1
### 12.3 Реальные сценарии
- **A-F** — все поддерживаются текущей моделью
- **F** — уже реализовано в 004
### 12.4 PurchaseItem vs Resource
- **PurchaseItem** — ordered quantity (обязательство)
- **Resource** — received quantity (фактическое поступление)
- **Decision** — без прямой FK связи (Вариант A)
### 12.5 Invoice Semantics
- **Invoice → Purchase** — N:1
- **Purchase → Project** — 1:1
- **Invoice → Project** — косвенно через Purchase
- **Decision** — косвенной связи достаточно
### 12.6 Specification Semantics
- **Specification → Project** — прямая FK
- **Purchase ↔ Specification** — M:N
- **Resource → Specification** — nullable FK
- **Decision** — nullable спецификация необходима для общих Resource
### 12.7 Provenance Chain
```
Specification → PurchaseSpecification → Purchase → PurchaseItem → Invoice → Resource → ResourceAllocation → System/Guardian/Common
```
### 12.8 Gaps
1. **Invoice → Project indirect link** — требует JOIN
2. **Specification ambiguity** — nullable specification_id
3. **Purchase vs Resource quantity** — нет проверки ordered/received
4. **Partial delivery** — нет поддержки частичных поставок
### 12.9 Recommended Task
**007-ProvenanceValidationService** — Service layer validation для procurement provenance
---
**Design завершен. Переход к следующей задаче НЕ производится.**
File diff suppressed because it is too large Load Diff
@@ -0,0 +1,626 @@
# Procurement Flow Domain Review v1
## 1. Executive Summary
**Задача:** 009-procurement-flow-domain-review-v1
**Дата:** 07 October 2026
**Рабочая директория:** `/mnt/nas/hermes-test/Specs`
**Тип:** Architecture / Domain Review (ТОЛЬКО обзор, без изменений кода)
**Цель:** Провести архитектурный gate после `008-procurement-flow-design-v2` — проверить корректность модели закупочного контура на уровне бизнес-семантики перед реализацией.
**Результат:** **PASS WITH CHANGES**
---
## 2. Findings Summary
### Finding 1: Module-level quantity validation
**Problem:** Текущая модель позволяет проверить `SUM(Resource.quantity) <= SUM(PurchaseItem.quantity)` только на уровне всей Purchase, а не по Module.
**Scenario:**
```
Purchase #10
PurchaseItem: Camera × 100
PurchaseItem: Agent × 100
Resource:
Camera × 200
```
**Analysis:**
- Общий `SUM(PurchaseItem.quantity) = 200`
- Общий `SUM(Resource.quantity) = 200`
- Проверка на уровне суммы проходит ✅
- Но по Module: `Camera: 200 received > 100 ordered` ❌
**Decision:** Проверка ordered vs received должна выполняться **по Module**, не по общей сумме.
**Impact:** Service layer должен выполнять модульную проверку.
---
### Finding 2: Resource.specification_id семантика
**Problem:** Неоднозначность: `Resource.specification_id` означает "партия относится к Specification" или "закрывает конкретную SpecificationItem"?
**Analysis:**
- Текущая модель связывает Resource с Specification на уровне Specification, не Item
- `SpecificationItem.quantity` — потребность, но проверка не выполняется на уровне Item
- Service layer валидирует Project match, но не Item-level fulfillment
**Decision:** `Resource.specification_id` означает **"эта полученная партия относится к Specification"** (provenance на уровне Specification), а не "закрывает конкретную SpecificationItem".
**Impact:** Service layer должен проверять `SUM(Resource.quantity) <= SpecificationItem.quantity` по Module.
---
### Finding 3: Purchase → Specification → Resource связь
**Problem:** Может ли Resource указывать Specification, которая не связана с его Purchase?
**Scenario:**
```
Purchase #10
PurchaseSpecification → Spec #12, Spec #18
Resource
Invoice → Purchase #10
Specification → Spec #999
```
где `Spec #999` принадлежит тому же Project, но не связана с Purchase #10.
**Analysis:**
- Текущая модель позволяет любую Specification из того же Project
- Это нарушает business rule: Resource должен относиться к Specification, связанной с Purchase
**Decision:** **Resource.specification_id должен быть связан с Purchase через PurchaseSpecification.**
**Impact:** Service layer должен проверять, что `Specification.id` находится в `Purchase.specifications`.
---
### Finding 4: Resource.semantics — Delivery vs Resource
**Problem:** Достаточно ли текущего `Resource` для частичных поставок, или нужна отдельная сущность `Delivery`?
**Analysis:**
- `Resource` = полученная партия (batch)
- `Delivery` = событие/документ поставки
- Частичная поставка: один Purchase → несколько поставок → несколько Resources
**Decision:** **Не создавать Delivery в рамках v1.**
**Reason:**
1. `Resource` уже хранит факт поступления (invoice, date, quantity)
2. `Invoice` может быть разделен на несколько `Resource`
3. `Shipment` существующая сущность для отгрузок
**Follow-up:** Рассмотреть `Delivery` для future enhancement если потребуется tracking отдельных событий поставки.
---
### Finding 5: Resource.invoice_id обязательность
**Problem:** Может ли Resource существовать без Invoice?
**Analysis:**
- Текущая модель: `invoice_id` nullable
- Business rule: Resource должен сохранять provenance до Invoice
**Decision:** **invoice_id должен быть NOT NULL.**
**Reason:**
1. Invoice — источник факта получения ресурса
2. Без Invoice невозможно проверить provenance
3. Business rule нарушается если Resource без Invoice
**Impact:** Изменить модель: `invoice_id` NOT NULL.
---
### Finding 6: Module mismatch в Resource
**Problem:** Допустим ли Resource с Module, которого нет в Specification?
**Scenario:**
```
Specification #12
Camera × 1000
Resource
Agent × 10
Specification = #12
```
**Analysis:**
- Resource имеет Module (Agent), которого нет в Specification
- Это нарушает business rule: Resource должен относиться к модулям Specification
**Decision:** **Resource.module_id должен быть в SpecificationItem.specification_id, module_id.**
**Impact:** Service layer должен проверять наличие Module в Specification.
---
### Finding 7: Multiple PurchaseItem одного Module
**Problem:** Разрешена ли модель с дублированием `(purchase_id, module_id)`?
**Scenario:**
```
Purchase #10
PurchaseItem: Camera × 1000
PurchaseItem: Camera × 500
```
**Analysis:**
- Текущая модель разрешает дублирование (нет UNIQUE constraint)
- Неясно, как сопоставлять Resource с ordered quantity
**Decision:** **Дублирование `(purchase_id, module_id)` должно быть запрещено на уровне DB.**
**Reason:**
1. Одна закупка → один заказанный quantity по Module
2. Дублирование создает неоднозначность
3. Service layer не может однозначно сопоставить Resource
**Impact:** Добавить UNIQUE constraint на `(purchase_id, module_id)`.
---
### Finding 8: Invoice как financial document
**Problem:** Не противоречит ли обязательность Invoice тому, что Invoice — financial document?
**Analysis:**
- Invoice хранит `amount` (financial sum)
- Resource хранит `quantity` (received amount)
- Нет явной связи quantity ↔ amount
**Decision:** **Invoice может быть только financial document, quantity через Resource.**
**Reason:**
1. `Invoice.amount` — сумма к оплате
2. `Resource.quantity` — полученное количество
3. Нет прямого соотношения quantity ↔ price
**Impact:** Никаких изменений, текущая модель корректна.
---
## 3. Quantity Validation — Module-level checks
### 3.1 Ordered vs Received per Module
**Business Rule:** Количество полученного ресурса по каждому Module не может превышать заказанное.
**Current Model:**
- `PurchaseItem.quantity` — ordered per Module per Purchase
- `Resource.quantity` — received per batch
**Validation Required:**
```python
# Для каждого Module в Purchase:
ordered = SUM(PurchaseItem.quantity)
received = SUM(Resource.quantity)
WHERE PurchaseItem.module_id = Module.id
AND Resource.module_id = Module.id
AND Resource.invoice.purchase = Purchase
assert received <= ordered
```
**Decision:** Проверка **обязательна по Module**, не по общей сумме.
**Impact:** Service layer должен выполнять модульную проверку.
---
### 3.2 Over-fulfillment of SpecificationItem
**Business Rule:** Количество ресурса, относящегося к SpecificationItem, не может превышать потребность.
**Scenario:**
```
SpecificationItem
Camera × 1000
Resource
Camera × 1200
Specification = #12
```
**Analysis:**
- `SpecificationItem.quantity` — потребность заказчика
- `Resource.quantity` — фактическое получение
- Over-fulfillment = `received > need`
**Decision:** **Service layer должен проверять `SUM(Resource.quantity) <= SpecificationItem.quantity` по Module.**
**Follow-up:** Бизнес-правило over-fulfillment (разрешено или запрещено?) должно быть определено.
**Impact:** Добавить проверку в ProvenanceValidationService.
---
## 4. Specification Provenance — Resource.specification_id
### 4.1 Точная семантика
**Question:** `Resource.specification_id` означает "партия относится к Specification" или "закрывает конкретную SpecificationItem"?
**Answer:** **Относится к Specification** (на уровне Specification, не Item).
**Reason:**
1. `Specification` хранит потребность (need)
2. `SpecificationItem` хранит потребность по Module
3. Resource связывается с Specification, не с Item
**Decision:** `Resource.specification_id` = provenance на уровне Specification.
**Impact:** Service layer должен проверять Module-level fulfillment через JOIN к SpecificationItem.
---
### 4.2 Resource → SpecificationItem связь
**Question:** Нужна ли прямая FK `Resource.specification_item_id`?
**Analysis:**
- Текущая модель: Resource → Specification (nullable)
- Проверка через JOIN: `Resource.module_id = SpecificationItem.module_id`
**Decision:** **Не создавать прямую FK.**
**Reason:**
1. Один Module может быть в нескольких SpecificationItem (редко, но возможно)
2. JOIN достаточно для проверки
3. Не усложнять модель без реальной необходимости
**Impact:** Service layer выполняет JOIN для проверки.
---
## 5. Resource Semantics — Delivery vs Resource
### 5.1 Resource как партия
**Decision:** `Resource = полученная партия (batch)`.
**Reason:**
1. Историческая запись о факте поступления
2. Сохраняет provenance: Invoice, Specification, Module, quantity
3. Не хранит остаток (вычисляется)
**Impact:** Текущая модель корректна.
---
### 5.2 Delivery как отдельный документ
**Question:** Нужна ли сущность Delivery?
**Analysis:**
- `Delivery` = событие/документ поставки
- `Shipment` уже существует (отгрузка)
- `Resource` хранит факт получения
**Decision:** **Не создавать Delivery в рамках v1.**
**Reason:**
1. `Resource` уже хранит факт получения (invoice, date, quantity)
2. `Shipment` может использоваться для отгрузок
3. Дополнительная сущность избыточна
**Follow-up:** Если потребуется tracking отдельных событий поставки — рассмотреть `Delivery` в future.
**Impact:** Никаких изменений.
---
## 6. Invoice и Resource
### 6.1 Обязательность invoice_id
**Question:** Может ли Resource существовать без Invoice?
**Decision:** **invoice_id должен быть NOT NULL.**
**Reason:**
1. Invoice — источник факта получения ресурса
2. Без Invoice невозможно проверить provenance
3. Business rule нарушается если Resource без Invoice
**Impact:** Изменить модель: `invoice_id` NOT NULL.
---
### 6.2 Invoice как financial document
**Decision:** Invoice может быть только financial document.
**Reason:**
1. `Invoice.amount` — сумма к оплате
2. `Resource.quantity` — полученное количество
3. Нет прямого соотношения
**Impact:** Текущая модель корректна.
---
## 7. Multiple PurchaseItem одного Module
### 7.1 Дублирование (purchase_id, module_id)
**Question:** Разрешено ли дублирование?
**Decision:** **Дублирование запрещено.**
**Reason:**
1. Одна закупка → один заказанный quantity по Module
2. Дублирование создает неоднозначность
3. Service layer не может однозначно сопоставить Resource
**Impact:** Добавить UNIQUE constraint: `UNIQUE(purchase_id, module_id)`.
---
### 7.2 Сопоставление Resource с PurchaseItem
**Decision:** **По module_id и date.**
**Reason:**
1. `Resource.module_id` сопоставляется с `PurchaseItem.module_id`
2. `Resource.invoice_date` сопоставляется с `PurchaseItem.date` (если есть)
3. Service layer выполняет JOIN и фильтрацию
**Impact:** Service layer выполняет сопоставление.
---
## 8. Consistency with 001–008
### 8.1 Проверка согласованности
| Решение 001–008 | Статус | Комментарий |
|-----------------|--------|-------------|
| **PurchaseItem = ordered** | ✅ | Подтверждено |
| **Resource = received** | ✅ | Подтверждено |
| **Resource.remaining вычисляется** | ✅ | Подтверждено |
| **Resource → Invoice** | ⚠️ | invoice_id должен быть NOT NULL |
| **Resource → Specification (nullable)** | ⚠️ | specification_id должен быть связан с Purchase |
| **Purchase ↔ Specification M:N** | ✅ | Подтверждено |
| **Один Invoice → несколько Resource** | ✅ | Подтверждено |
| **Один Resource → несколько allocations** | ✅ | Подтверждено |
| **Общий пул проекта** | ✅ | Подтверждено |
| **No InvoiceItem** | ✅ | Подтверждено |
| **No PurchaseItem → SpecificationItem link** | ✅ | Подтверждено |
### 8.2 Выявленные проблемы
| # | Проблема | Severity | Требуется |
|---|----------|----------|-----------|
| 1 | invoice_id nullable | Medium | Сделать NOT NULL |
| 2 | specification_id не проверяет связь с Purchase | Medium | Service layer проверка |
| 3 | Нет UNIQUE на (purchase_id, module_id) | Medium | Добавить constraint |
| 4 | Module-level validation отсутствует | High | Service layer проверка |
| 5 | Over-fulfillment не проверяется | High | Service layer проверка |
---
## 9. Accepted Decisions
### Decision 1: Module-level quantity validation
**Decision:** Проверка ordered vs received должна выполняться **по Module**, не по общей сумме.
**Reason:** Бизнес-правило требует соответствия по каждому Module.
**Impact:** Service layer должен выполнять модульную проверку.
---
### Decision 2: Resource.specification_id = provenance на уровне Specification
**Decision:** `Resource.specification_id` означает "партия относится к Specification", не "закрывает SpecificationItem".
**Reason:** Specification хранит потребность, не Item-level tracking.
**Impact:** Service layer выполняет JOIN к SpecificationItem.
---
### Decision 3: Resource.specification_id связан с Purchase
**Decision:** Specification у Resource должна быть связана с Purchase через PurchaseSpecification.
**Reason:** Business rule: Resource относится к Specification закупки.
**Impact:** Service layer проверяет связь.
---
### Decision 4: invoice_id NOT NULL
**Decision:** `Resource.invoice_id` должен быть NOT NULL.
**Reason:** Invoice — источник факта получения.
**Impact:** Изменить модель.
---
### Decision 5: Unique (purchase_id, module_id)
**Decision:** Запретить дублирование `(purchase_id, module_id)`.
**Reason:** Избегать неоднозначности сопоставления.
**Impact:** Добавить constraint.
---
### Decision 6: Module в Specification
**Decision:** Resource.module_id должен быть в SpecificationItem.
**Reason:** Business rule: Resource относится к модулям Specification.
**Impact:** Service layer проверяет.
---
## 10. Changes Required Before Implementation
### Priority 1: High
**Change 1:** Добавить Module-level validation в Service layer.
**Description:** Проверка `SUM(Resource.quantity) <= SUM(PurchaseItem.quantity)` по каждому Module.
**Impact:** ProvenanceValidationService.
---
**Change 2:** Добавить проверку over-fulfillment в Service layer.
**Description:** Проверка `SUM(Resource.quantity) <= SpecificationItem.quantity` по каждому Module.
**Impact:** ProvenanceValidationService.
---
**Change 3:** Добавить проверку связи Specification с Purchase.
**Description:** Проверка, что `Resource.specification_id` находится в `Purchase.specifications`.
**Impact:** ProvenanceValidationService.
---
### Priority 2: Medium
**Change 4:** Сделать `Resource.invoice_id` NOT NULL.
**Description:** Изменить модель: `invoice_id` NOT NULL.
**Impact:** Alembic migration.
---
**Change 5:** Добавить UNIQUE constraint на `(purchase_id, module_id)`.
**Description:** Добавить `UNIQUE(purchase_id, module_id)` в PurchaseItem.
**Impact:** Alembic migration.
---
### Priority 3: Low
**Change 6:** Рассмотреть Delivery для future enhancement.
**Description:** Если потребуется tracking отдельных событий поставки.
**Impact:** Future task.
---
## 11. Deferred Questions
### Question 1: Over-fulfillment policy
**Question:** Должна ли система запрещать over-fulfillment (получение больше, чем потребность)?
**Answer:** **Service layer должен поддерживать политику.**
**Reason:** Business rules могут меняться.
**Follow-up:** Определить политику (запрещено / разрешено с warning).
---
### Question 2: Delivery tracking
**Question:** Нужно ли отслеживать отдельные события поставки?
**Answer:** **Нет в рамках v1.**
**Reason:** Resource уже хранит факт получения.
**Follow-up:** Рассмотреть если потребуется детальное tracking событий.
---
### Question 3: Partial delivery semantics
**Question:** Как точно моделировать частичные поставки?
**Answer:** **Через множественные Resource.**
**Reason:** Каждая частичная поставка → отдельный Resource.
**Follow-up:** Добавить дату/номер поставки в Resource.
---
## 12. Final Gate Decision
### **PASS WITH CHANGES**
Архитектура закупочного контура в целом годится, но перед implementation необходимо внести конкретные изменения в design.
---
### Изменения перед implementation:
#### Must Have (до начала реализации):
1. **Module-level validation:** Добавить проверку ordered vs received по Module в Service layer.
2. **Over-fulfillment check:** Добавить проверку против SpecificationItem.quantity в Service layer.
3. **Purchase-Specification link:** Добавить проверку, что Specification у Resource связана с Purchase в Service layer.
#### Should Have (желательно до начала реализации):
4. **invoice_id NOT NULL:** Изменить модель: `invoice_id` NOT NULL.
5. **Unique (purchase_id, module_id):** Добавить UNIQUE constraint.
#### Could Have (можно после начала реализации):
6. **Delivery tracking:** Рассмотреть для future enhancement.
7. **Partial delivery semantics:** Добавить поле delivery_date/delivery_number в Resource.
---
## 13. Summary
### 13.1 Ключевые findings
1. **Module-level validation:** Проверка ordered vs received должна быть по Module, не по общей сумме.
2. **Specification provenance:** `Resource.specification_id` = provenance на уровне Specification.
3. **Purchase-Specification link:** Specification у Resource должна быть связана с Purchase.
4. **invoice_id:** Должен быть NOT NULL.
5. **Unique constraint:** Запретить дублирование (purchase_id, module_id).
6. **Module in Specification:** Resource.module_id должен быть в SpecificationItem.
### 13.2 Изменения перед implementation
**High priority:**
- Module-level validation
- Over-fulfillment check
- Purchase-Specification link check
**Medium priority:**
- invoice_id NOT NULL
- Unique constraint
### 13.3 Consistency
Архитектура согласована с 001–008. Все выявленные проблемы могут быть решены Service layer или minor schema changes.
---
**Review завершен. Переход к следующей задаче НЕ производится.**